Od pierwszego wykopu — co miesiąc
Każdą budowę dokumentujemy w stałym rytmie: ten sam kadr co miesiąc, data, etap, fakty. Najmocniejszy dowód terminowości to sekwencja zdjęć z tego samego punktu.
- 05.2026Structure· Stacja Wilga
Slab over the third floor poured; the brick coursing of the front facade begins.
Structure on schedule — the weather buffer from March is still unused. On the boulevard front, the first metres of brick in the coursing known from the siding wall.
- 04.2026Structure· Stacja Wilga
Third-storey walls; the lift shaft up to level +3.
The load-bearing wall of building A has reached the third floor. In parallel we are running the under-floor services on the ground floor.
- 03.2026Structure· Stacja Wilga
Stage I handed over on time; stage II — slab over the ground floor.
Stage I accepted 03.2026, on time to the month per contract. On stage II the slab over the ground floor of building A is closed.
- 02.2026Excavation & foundations· Stacja Wilga
Foundation slab of building A — poured.
Foundation-slab concreting finished. Frost did not delay the work — pouring took place in a weather window with a heated mix.